Which statement describes how Kanban teams handle capacity during PI Planning?

They use historical data to estimate future capacity

They use throughput as an indication of their capacity

Kanban teams utilize throughput as an indication of their capacity, which aligns well with the principles of the Kanban methodology. Throughput refers to the amount of work items that a team can complete in a specific time frame, providing a practical and data-driven basis for understanding the team's capacity. By focusing on throughput, Kanban teams can make more informed decisions regarding how much work they can realistically commit to during Program Increment (PI) Planning.

This approach allows teams to avoid over-committing and helps to manage flow effectively by understanding past performance. It emphasizes continuous improvement by enabling teams to analyze their historical throughput data to anticipate future capacity, ensuring that they work within their limits and maintain a sustainable pace. As a result, this practice supports better planning and enhances the ability to deliver value consistently.

Get further explanation with Examzify DeepDiveBeta

They rely on team members' personal estimates of work

They set fixed capacity limits for the entire program